Depending on the criticality and complexity of the materials & equipment being procured, CLIENT and their assigned representatives may conduct out a pre-award audit or assessment of CONTRACTOR & VENDOR and any intended lower-tier- Supply Chain prior to the award …
Project Quality Plan (PQP) is normally required for criticality “1” packages. It is based on ISO 10005 Quality management — Guidelines for quality plans. It would have the same requirements as ISO 9001 QMS but intended for implementation at project …
ISR can be based on Procurement status report (PSR) with focus on inspection. ISR is updated and turned around internally on weekly basis. Information in a typical ISR can include all of the information in a typical PSR; plus: …
It is a good practice to have a PSR that acts as a dashboard for procurement and fabrication activities updated on weekly basis. The Procurement Status Report normally shows: Name of package Name of supplier Name of relevant team …
[su_box title="Free API SIRE Practice Questions" style="soft" box_color="#0213eb" radius="10"] This quiz must be completed in 20 minutes. Click here to start the quiz 1200 <<1234567891011121314151617181920>> 0% Loading... [/su_box] Source Inspector is defined as an individual who is responsible for: …