Procurement Status Report (PSR)

Share This Post

 

It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis.

 

The Procurement Status Report normally shows:

  • Name of package
  • Name of supplier
  • Name of relevant team members (package engineer, quality engineer, buyer, expeditor, lead inspector)
  • Date the Purchase order signed off,
  • Dates for Kick Off Meeting (K O M), Pre Inspection Meeting (P I M), Fabrication Commencement Date, Bench Mark Dates Fabrication and Testing, latest expediting visit and report Number.
  • Dates for First release, last release, Required on Site (R O S) Date and the like.

 

Required on Site date is normally a couple of months after the release date in order to absorb any delay in manufacturing and release without affecting the project progress. 

 

 

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

Difference between Codes & Recommended Practices (RP)

Codes are mandatory. It is mandated by jurisdiction or the project. You can not violate or ignore a code requirement else, you are not complying with the code. For example, if a pressure vessel is built and stamped as per

Electorde polarity

When butt welding a pipeline, achieving strenght weld is crucial, a weldment with good penetration. To ensure this, connecting the electrode to the negative pole is essential. This setup generates more heat at the base metal, reducing electrode burn rate

Do You Want To Boost Your knowledge?

See our Coursses