Procurement Status Report (PSR)

Share This Post

 

It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis.

 

The Procurement Status Report normally shows:

  • Name of package
  • Name of supplier
  • Name of relevant team members (package engineer, quality engineer, buyer, expeditor, lead inspector)
  • Date the Purchase order signed off,
  • Dates for Kick Off Meeting (K O M), Pre Inspection Meeting (P I M), Fabrication Commencement Date, Bench Mark Dates Fabrication and Testing, latest expediting visit and report Number.
  • Dates for First release, last release, Required on Site (R O S) Date and the like.

 

Required on Site date is normally a couple of months after the release date in order to absorb any delay in manufacturing and release without affecting the project progress. 

 

 

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

Inspector Continuous Improvement

  Continuous Improvement: At the completion of the inspection activities; a PDCA cycle (plan, do, check, act) review is taken as part of a continuous improvement program to determine which activities went well and where improvements should be made. Any

Maximum Allowable Working Pressure (MAWP)

  It is the maximum gauge pressure at the top of a pressure vessel allowed by design or code calculations for a set temperature. When the working temperature decreases or significantly increases, material strength is reduced and therefore the pressure

Do You Want To Boost Your knowledge?

See our Coursses