It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis.

 

The Procurement Status Report normally shows:

  • Name of package
  • Name of supplier
  • Name of relevant team members (package engineer, quality engineer, buyer, expeditor, lead inspector)
  • Date the Purchase order signed off,
  • Dates for Kick Off Meeting (K O M), Pre Inspection Meeting (P I M), Fabrication Commencement Date, Bench Mark Dates Fabrication and Testing, latest expediting visit and report Number.
  • Dates for First release, last release, Required on Site (R O S) Date and the like.

 

Required on Site date is normally a couple of months after the release date in order to absorb any delay in manufacturing and release without affecting the project progress. 

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

🛢️ API 653 — 1-PAGE ULTRA CHEAT SHEET

  🧮 CORE FORMULAS (MEMORIZE ONLY THESE) 📉 Corrosion Rate (CR) CR=tinitial−tcurrenttimeCR = \frac{t_{initial} – t_{current}}{time}CR=timetinitial​−tcurrent​​ ➡️ Always subtract initial − current     ⏳ Remaining Life (RL) RL=t−tminCRRL = \frac{t – t_{min}}{CR}RL=CRt−tmin​​     📅 Inspection Interval Interval=RL2Interval =

Top 30 API 653 Calculation Problems with Full Solutions

Here’s your Top 30 API 653 Calculation Problems with Full Solutions—focused on real exam patterns: corrosion, remaining life, thickness, hydrostatic pressure, and decision logic. Use this to build speed + confidence. 🛢️ API 653 — TOP 30 CALCULATION QUESTIONS (WITH

Do You Want To Boost Your knowledge?

See our Coursses