Procurement Status Report (PSR)

Share This Post

 

It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis.

 

The Procurement Status Report normally shows:

  • Name of package
  • Name of supplier
  • Name of relevant team members (package engineer, quality engineer, buyer, expeditor, lead inspector)
  • Date the Purchase order signed off,
  • Dates for Kick Off Meeting (K O M), Pre Inspection Meeting (P I M), Fabrication Commencement Date, Bench Mark Dates Fabrication and Testing, latest expediting visit and report Number.
  • Dates for First release, last release, Required on Site (R O S) Date and the like.

 

Required on Site date is normally a couple of months after the release date in order to absorb any delay in manufacturing and release without affecting the project progress. 

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

Most Repeated Question Types for API SIRE Examination

These formats repeat a lot: ✅ Scenario-based “During inspection, vendor refuses access. What should inspector do?” 👉 Answer usually: Escalate / notify purchaser Follow procedure (NOT argue)   ✅ Definition-based “What is hold point vs witness point?” ✅ “Best action”

Most Repeated API SIRE Questions Areas

These are the high-frequency topics (based on exam breakdown + practice banks):   Source Inspection Basics Roles & responsibilities of inspector Authority (e.g. SIMP vs ITP vs PO) Ethics & communication 📌 Example: “Which document defines inspector authority?” ✔ Answer:

Do You Want To Boost Your knowledge?

See our Coursses