🔹 1. Vendor refuses inspection access
🔹 1. What should the inspector do FIRST?
A. Stop work
B. Leave site
C. Escalate to purchaser
D. Argue
👉 Answer: C – Escalate
❗ Trap: Many pick “stop work” → but inspector has no authority to stop vendor operations
🔹 2. Minor deviation found
- Accept it
B. Ignore
C. Approve
D. Report to purchaser
👉 Answer: D – Report
❗ Inspector NEVER approves deviations
🔹 3. Missing ITP at site
- Continue inspection
B. Use experience
C. Stop and report
D. Ask technician
👉 Answer: C – Stop and report
❗ No ITP = no controlled inspection
🔹 4. Vendor asks for verbal approval
- Approve
B. Ignore
C. Decline and escalate
D. Accept temporarily
👉 Answer: C
❗ No verbal approvals—everything must be documented
🔹 5. Two documents conflict (PO vs ITP)
- Follow ITP
B. Follow vendor
C. Escalate
D. Choose best
👉 Answer: C – Escalate
❗ Never assume hierarchy in conflict—clarify
🔹 6. Witness point missed
- Reject work
B. Accept automatically
C. Review records and report
D. Ignore
👉 Answer: C
❗ Witness ≠ mandatory stop (that’s hold point)
🔹 7. Hold point passed without inspector
- Accept
B. Reject immediately
C. Escalate
D. Ignore
👉 Answer: C – Escalate
❗ Don’t auto-reject—follow process
🔹 8. Unsafe condition observed
- Ignore
B. Continue inspection
C. Report immediately
D. Leave site
👉 Answer: C
❗ Safety overrides everything
🔹 9. Inspector unsure about spec requirement
- Guess
B. Ask vendor
C. Escalate / clarify
D. Skip
👉 Answer: C
❗ Never rely on vendor interpretation
🔹 10. Vendor offers gift
- Accept politely
B. Decline and report
C. Ignore
D. Accept small items
👉 Answer: B
❗ Ethics = zero tolerance
🔹 11. NDT report shows borderline result
- Accept
B. Reject
C. Escalate for clarification
D. Ignore
👉 Answer: C
❗ Inspector doesn’t make final engineering judgment
🔹 12. Drawing revision mismatch
- Continue
B. Use latest available
C. Stop and report
D. Ask worker
👉 Answer: C
❗ Revision control is critical
🔹 13. Equipment passes test but docs incomplete
- Accept
B. Reject
C. Hold until docs complete
D. Ignore
👉 Answer: C
❗ Documentation = part of compliance
🔹 14. Vendor pressures inspector to sign
- Sign
B. Delay
C. Refuse and escalate
D. Ignore
👉 Answer: C
❗ No pressure-based decisions
🔹 15. Non-critical defect found
- Ignore
B. Accept
C. Document and report
D. Fix yourself
👉 Answer: C
❗ Even minor issues must be recorded
🔹 16. Calibration certificate expired
- Use tool anyway
B. Ignore
C. Stop and report
D. Adjust manually
👉 Answer: C
❗ Uncalibrated tools = invalid inspection
🔹 17. Vendor procedure differs from spec
- Follow vendor
B. Follow spec
C. Escalate
D. Ignore
👉 Answer: C
❗ Always resolve conflict formally
🔹 18. Inspector arrives late for hold point
- Accept work
B. Reject work
C. Escalate
D. Ignore
👉 Answer: C
❗ Same logic: no unilateral decisions
🔹 19. Test results acceptable but method incorrect
- Accept
B. Reject
C. Escalate
D. Ignore
👉 Answer: C
❗ Process matters as much as result
🔹 20. Vendor says “this is standard practice”
- Accept
B. Reject
C. Verify against specs
D. Ignore
👉 Answer: C
❗ Never rely on vendor claims