Depending on the criticality and complexity of the materials & equipment being procured, CLIENT and their assigned representatives may conduct out a pre-award audit or assessment of CONTRACTOR & VENDOR and any intended lower-tier- Supply Chain prior to the award
Normally, 2-4 weeks after the kick off meeting or 2 weeks after submission of critical quality documents, the pre production meeting is held. It is advisable to hold the PIM after one cycle of critical document turnaround in order to