Prepare a Cost Time Report (CTR) for each package to calculate the budget in terms of inspection man days required during manufacturing.

 

You can use equipment criticality to assign a factor for calculating man days.

 

For example, for  an equipment with criticality “1” , assign a factor of “1.6”;

 

Now; if the equipment takes 6 months to be manufactured; considering 5 working days per week, you would need 6 X 22 (22 being working days in a month) multiplied by 1.6 (package criticality factor) = 211 man days of inspection.

 

For criticality “2” you can use a factor of “1” and so on.

 

Criticality “3” normally needs a final inspection only; while criticality “4” items are normally inspected at the point of receipt or at site.

 

You may want to add 25% to the total budget to account for uncertainties and any surprises such as:

  •  repeat inspection due to NCR,
  •  cancelled inspection by supplier,
  •  delays,
  •  enhanced inspection due to supplier’s poor performance.

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

API 580 sample questions
Api 580

API 580 Sample Questions | Free Practice Test

    Click to view Free Quiz   20 API 580 SamplePractice Questions     There are four definite leads to help you understand what type of questions to expect during examination. These are: API RP 580 Risk-based Inspection, Third

How heat exchanger works

https://static.inspector-training.com/uploads/2023/06/How-heat-exchanger-works.mp4

Do You Want To Boost Your knowledge?

See our Coursses