Order of Precedence for Reference Documents

Share This Post

 

The supplier shall adhere to the instructions and reference documents included in the purchase order.

 

In case of discrepancy between reference documents, normally, the following order of precedence is observed:

  1. Contract, Specific Conditions
  2. Contract, General Conditions
  3. Basis of Design (B O D)
  4. Documents that require deviation to be approved by Client including Design Criteria, Philosophies, PFDs, Plot Plans
  5. Documents that require deviation to be approved by Principal Contractor including Specifications,  drawings.

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

🛢️ API 653 Exam tips

  🧮 CORE FORMULAS (MEMORIZE ONLY THESE) 📉 Corrosion Rate (CR) CR =  t initial−t actual/ years in service ➡️ Always subtract initial − actual     ⏳ Remaining Life (RL) RL = t initial−t current / CR    

Top 30 API 653 Calculation Problems with Full Solutions

Here’s your Top 30 API 653 Calculation Problems with Full Solutions—focused on real exam patterns: corrosion, remaining life, thickness, hydrostatic pressure, and decision logic. Use this to build speed + confidence. 🛢️ API 653 — TOP 30 CALCULATION QUESTIONS (WITH

Do You Want To Boost Your knowledge?

See our Coursses