Order of Precedence for Reference Documents

Share This Post

 

The supplier shall adhere to the instructions and reference documents included in the purchase order.

 

In case of discrepancy between reference documents, normally, the following order of precedence is observed:

  1. Contract, Specific Conditions
  2. Contract, General Conditions
  3. Basis of Design (B O D)
  4. Documents that require deviation to be approved by Client including Design Criteria, Philosophies, PFDs, Plot Plans
  5. Documents that require deviation to be approved by Principal Contractor including Specifications,  drawings.

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

API 580 sample questions
Api 580

API 580 Sample Questions | Free Practice Test

    Click to view Free Quiz   20 API 580 SamplePractice Questions     There are four definite leads to help you understand what type of questions to expect during examination. These are: API RP 580 Risk-based Inspection, Third

How heat exchanger works

https://static.inspector-training.com/uploads/2023/06/How-heat-exchanger-works.mp4

Do You Want To Boost Your knowledge?

See our Coursses