API 653 exam-style questions 

 

🧮 SECTION 1 — CORROSION / REMAINING LIFE (Q1–Q10)

Q1: Thickness drops from $0.500″ to 0.350″ over 5 years. What is the corrosion rate (CR)?

Answer: {0.500 – 0.350}/{5} = 0.030 in/yr

Exam Note: Always confirm the unit requested (e.g., mils/yr vs. in/yr).

 

 

 

 

Q2. tactual = 0.300 in, tmin = 0.200 in, CR = 0.020; Remaining life?

Answer: {0.300 – 0.200}/0.020}=  5 years

 

 

 

 

Q3. Remaining life = 6 years; Next inspection interval?

Answer: 3 years

 

 

 

 

Q4. If corrosion rate doubles, remaining life:

A) Doubles
B) Halves
C) Same
D) Increases slightly

Answer: It halves (B). Remaining life is inversely proportional to the corrosion rate.

 

 

 

 

Q5. Thickness loss from 0.600 → 0.450 in; % loss?

25%

 

 

 

Q6. Bottom plate corrosion is typically:

A) Internal only
B) External soil side
C) Weld only
D) Roof only

Answer: External soil side (B). Unprotected soil contact and moisture entrapment make the underside the primary target for aggressive corrosion.

 

 

 

Q7. Corrosion rate unit is:

A) psi/year
B) in/year
C) ft/year
D) MPa/year

Answer: inches/year (in/yr) or mils/year (B)

 

 

 

 

Q8. Remaining life depends on:

A) Pressure only
B) Thickness + corrosion rate
C) Temperature only
D) Weld type

Answer: Current thickness, minimum allowable thickness, and corrosion rate (B).

 

 

 

 

Q9. Minimum thickness exceeded means:

A) Safe indefinitely
B) Action required
C) No inspection needed
D) Ignore

Answer: Immediate action is required (B). The component is no longer fit for service at its current operating parameters.

 

 

 

 

Q10. Corrosion allowance is:

A) Extra thickness for future loss
B) Pressure factor
C) Weld property
D) Inspection interval

Answer: Extra sacrificial thickness added during design to accommodate expected metal loss over the service life (A).

 

 

 

 

 

📏 SECTION 2 — THICKNESS & FITNESS (Q11–Q20)

Q11. Shell thickness is lowest at:

A) Top
B) Bottom
C) Middle
D) Same everywhere

Answer: At the top course (A). Hydrostatic pressure drops to zero at the liquid design level, requiring less structural thickness.

 

 

 

 

Q12. Highest stress in tank shell occurs at:

A) Top course
B) Middle
C) Bottom course
D) Roof

Answer: At the bottom course (C). This zone experiences maximum total hydrostatic head.

 

 

 

 

Q13. Hydrostatic pressure increases with:

A) Temperature
B) Height
C) Thickness
D) Weld quality

Answer: Liquid height/head (B). Calculated via P = 0.433 x H x {SG}

 

 

 

 

Q14. If thickness < minimum:

A) Continue operation
B) Repair or de-rate
C) Ignore
D) Increase pressure

Answer: Repair it, de-rate the maximum fill height, or perform an advanced fitness-for-service (API 579) evaluation (B).

 

 

 

 

Q15. Annular ring is located at:

A) Roof
B) Shell-bottom junction
C) Nozzle
D) Foundation top

Answer: At the shell-to-bottom plate junction (B). It acts as a critical structural tie-in to distribute high shell bending stresses.

 

 

 

 

Q16. Bottom plate failure is mainly due to:

A) Pressure
B) Soil corrosion
C) Wind
D) Heat

Answer: Undetected soil-side corrosion (B)

 

 

 

 

Q17. Shell stress is proportional to:

A) Height of liquid
B) Paint
C) Color
D) Weld length

Answer: The height of the liquid column above that point (A).

 

 

 

 

Q18. Which reduces stress?

A) Increase height
B) Reduce fill level
C) Increase pressure
D) Remove thickness

Answer: Lowering the maximum fill level (B). This reduces the total hydrostatic head.

 

 

 

 

Q19. Thickness evaluation determines:

A) Color
B) Fitness for service
C) Inspection method
D) Welding type

Answer: To establish structural integrity and ongoing fitness for service (B).

 

 

 

 

Q20. Bottom inspection requires:

A) External only
B) Internal inspection
C) No inspection
D) Painting

Answer: An internal inspection (B). Out-of-service NDE (like MFL or UT scan) is required to evaluate floor plate condition accurately.

 

 

 

 

 

🔍 SECTION 3 — INSPECTION & INTERVALS (Q21–Q30)

Q21. Inspection interval is based on:

A) Age
B) Remaining life
C) Pressure only
D) Color

✔ B) Remaining life
➡️ Core governing factor

 

 

 

 

Q22. External inspection detects:

A) Bottom corrosion
B) Shell condition
C) Internal pitting
D) Soil corrosion

✔ B) Shell condition
➡️ External checks visible surfaces

 

 

 

 

Q23. Internal inspection detects:

A) External cracks
B) Bottom corrosion
C) Paint defects
D) Wind damage

✔ B) Bottom corrosion
➡️ Requires internal inspection

 

 

 

 

Q24. On-stream inspection means:

A) Tank empty
B) Tank in service
C) Tank dismantled
D) Tank repaired

✔ B) Tank in service
➡️ On-stream = operating condition

 

 

 

 

Q25. Maximum interval is:

A) RL × 2
B) RL ÷ 2
C) RL
D) RL + 10

✔ B) RL ÷ 2
➡️ Maximum interval rule

 

 

 

 

Q26. RBI allows:

A) Ignoring inspection
B) Adjusting interval
C) Removing corrosion
D) Eliminating thickness

✔ B) Adjusting interval
➡️ Risk-based inspection flexibility

 

 

 

 

Q27. Inspection determines:

A) Pressure only
B) Condition of tank
C) Color
D) Weld type

✔ B) Condition of tank
➡️ Inspection = condition assessment

 

 

 

 

Q28. Frequency increases when:

A) Corrosion increases
B) Thickness increases
C) Paint improves
D) Height decreases

✔ A) Corrosion increases
➡️ Faster degradation → more frequent inspection

 

 

 

 

Q29. Inspection must be documented by:

A) Operator
B) Inspector
C) Welder
D) Painter

✔ B) Inspector
➡️ Authorized inspector responsibility

 

 

 

 

Q30. Inspection plan is based on:

A) Risk + condition
B) Color
C) Weld size
D) Roof type

✔ A) Risk + condition
➡️ Core inspection planning logic

 

 

 

 

 

🧱 SECTION 4 — DAMAGE MECHANISMS (Q31–Q40)

Q31. MIC stands for:

A) Mechanical impact
B) Microbiological corrosion
C) Magnetic inspection
D) Material inconsistency

✔ B) Microbiological induced corrosion (MIC)
➡️ Bacteria-driven corrosion

 

 

 

 

Q32. CUI occurs due to:

A) Heat
B) Insulation moisture
C) Pressure
D) Welding

✔ B) Insulation moisture
➡️ Traps water → corrosion

 

 

 

 

Q33. Pitting corrosion is:

A) Uniform
B) Localized
C) Weld only
D) External only

✔ B) Localized
➡️ Pitting is concentrated damage

 

 

 

 

Q34. Settlement causes:

A) Color change
B) Stress concentration
C) Pressure drop
D) Temperature rise

✔ B) Stress concentration
➡️ Uneven settlement creates stress

 

 

 

 

Q35. Edge settlement affects:

A) Roof
B) Shell-bottom area
C) Nozzle only
D) Paint

✔ B) Shell-bottom area
➡️ Critical stress region

 

 

 

 

Q36. Uniform settlement is:

A) Dangerous always
B) Usually acceptable
C) Always failure
D) Impossible

✔ B) Usually acceptable
➡️ If uniform, less damaging

 

 

 

Q37. Bottom corrosion risk increases with:

A) Dry soil
B) Wet soil
C) Paint
D) Thickness

✔ B) Wet soil
➡️ Promotes corrosion

 

 

 

Q38. Thermal effects cause:

A) Settlement
B) Expansion/contraction
C) Corrosion
D) Welding

✔ B) Expansion/contraction
➡️ Thermal cycling effect

 

 

 

Q39. Damage mechanism selection depends on:

A) Color
B) Environment + service
C) Thickness only
D) Pressure only

✔ B) Environment + service
➡️ Determines damage type

 

 

 

Q40. Most critical tank failure area:

A) Roof
B) Bottom
C) Paint
D) Ladder

✔ B) Bottom
➡️ Most failures originate here

 

 

 

⚙️ SECTION 5 — REPAIRS / ALTERATIONS (Q41–Q50)

Q41. Repair means:

A) Change design
B) Restore original condition
C) Increase height
D) Replace entire tank

✔ B) Restore original condition
➡️ Repair definition

 

 

 

Q42. Alteration means:

A) Restore condition
B) Change design
C) Paint tank
D) Inspect

✔ B) Change design
➡️ Alteration definition

 

 

 

Q43. Reconstruction means:

A) Minor repair
B) Rebuilding tank
C) Painting
D) Inspection

✔ B) Rebuilding tank
➡️ Reconstruction concept

 

 

 

Q44. Welding repair requires:

A) Approval
B) Paint
C) Inspection only
D) Nothing

✔ A) Approval
➡️ Required before welding repair

 

 

 

Q45. Bottom replacement is:

A) Repair
B) Alteration
C) Reconstruction
D) Inspection

✔ A) Repair
➡️ Bottom replacement restores function

 

 

 

Q46. Shell course replacement is:

A) Repair
B) Alteration
C) Reconstruction
D) Painting

✔ C) Reconstruction
➡️ Major structural rebuild

 

 

 

Q47. Documentation is required for:

A) Inspection only
B) Repairs and alterations
C) Painting
D) Color change

✔ B) Repairs and alterations
➡️ Must be documented

 

 

 

Q48. Hydrotest after repair is:

A) Always required
B) Sometimes required
C) Never required
D) Only for paint

✔ B) Sometimes required
➡️ Depends on repair type

 

 

 

Q49.Who approves repair?

A) Operator only
B) Authorized inspector
C) Welder
D) Painter

✔ B) Authorized inspector
➡️ Final approval authority

 

 

 

Q50. Fitness-for-service decision is based on:

A) Thickness + condition
B) Color
C) Height
D) Paint

✔ A) Thickness + condition
➡️ Determines safety decision

 

 

 

 

🧠 PATTERN SUMMARY

🧮 Calculation logic:

  • Corrosion rate → thickness loss over time
  • Remaining life → usable thickness / CR
  • Inspection interval → RL ÷ 2

 

📏 Tank logic:

  • Bottom = highest risk
  • Height ↑ → pressure ↑ → stress ↑
  • Thickness ↓ → risk ↑

 

 

 

🔍 Inspection logic:

  • External → shell
  • Internal → bottom
  • RBI → adjust interval

 

 

 

⚙️ Repair logic:

  • Repair = restore
  • Alteration = change
  • Reconstruction = rebuild

 

 

want to know more? study our free lessons and quiz at:

API 653 Storage Tank Inspector Online Training Course

 

 

 

 

Take the Next Step in Your Inspection Career

Explore our API, NDT and CPD training courses.

Explore All Courses →