CPD Accredited Provider ◆ 100% Online & Self-Paced ◆ Trusted by inspectors in 70+ countries

API 653 exam-style questions 

Share This Post

 

🧮 SECTION 1 — CORROSION / REMAINING LIFE (Q1–Q10)

Q1: Thickness drops from $0.500″ to 0.350″ over 5 years. What is the corrosion rate (CR)?

Answer: {0.500 – 0.350}/{5} = 0.030 in/yr

Exam Note: Always confirm the unit requested (e.g., mils/yr vs. in/yr).

 

 

 

 

Q2. tactual = 0.300 in, tmin = 0.200 in, CR = 0.020; Remaining life?

Answer: {0.300 – 0.200}/0.020}=  5 years

 

 

 

 

Q3. Remaining life = 6 years; Next inspection interval?

Answer: 3 years

 

 

 

 

Q4. If corrosion rate doubles, remaining life:

A) Doubles
B) Halves
C) Same
D) Increases slightly

Answer: It halves (B). Remaining life is inversely proportional to the corrosion rate.

 

 

 

 

Q5. Thickness loss from 0.600 → 0.450 in; % loss?

25%

 

 

 

Q6. Bottom plate corrosion is typically:

A) Internal only
B) External soil side
C) Weld only
D) Roof only

Answer: External soil side (B). Unprotected soil contact and moisture entrapment make the underside the primary target for aggressive corrosion.

 

 

 

Q7. Corrosion rate unit is:

A) psi/year
B) in/year
C) ft/year
D) MPa/year

Answer: inches/year (in/yr) or mils/year (B)

 

 

 

 

Q8. Remaining life depends on:

A) Pressure only
B) Thickness + corrosion rate
C) Temperature only
D) Weld type

Answer: Current thickness, minimum allowable thickness, and corrosion rate (B).

 

 

 

 

Q9. Minimum thickness exceeded means:

A) Safe indefinitely
B) Action required
C) No inspection needed
D) Ignore

Answer: Immediate action is required (B). The component is no longer fit for service at its current operating parameters.

 

 

 

 

Q10. Corrosion allowance is:

A) Extra thickness for future loss
B) Pressure factor
C) Weld property
D) Inspection interval

Answer: Extra sacrificial thickness added during design to accommodate expected metal loss over the service life (A).

 

 

 

 

 

📏 SECTION 2 — THICKNESS & FITNESS (Q11–Q20)

Q11. Shell thickness is lowest at:

A) Top
B) Bottom
C) Middle
D) Same everywhere

Answer: At the top course (A). Hydrostatic pressure drops to zero at the liquid design level, requiring less structural thickness.

 

 

 

 

Q12. Highest stress in tank shell occurs at:

A) Top course
B) Middle
C) Bottom course
D) Roof

Answer: At the bottom course (C). This zone experiences maximum total hydrostatic head.

 

 

 

 

Q13. Hydrostatic pressure increases with:

A) Temperature
B) Height
C) Thickness
D) Weld quality

Answer: Liquid height/head (B). Calculated via P = 0.433 x H x {SG}

 

 

 

 

Q14. If thickness < minimum:

A) Continue operation
B) Repair or de-rate
C) Ignore
D) Increase pressure

Answer: Repair it, de-rate the maximum fill height, or perform an advanced fitness-for-service (API 579) evaluation (B).

 

 

 

 

Q15. Annular ring is located at:

A) Roof
B) Shell-bottom junction
C) Nozzle
D) Foundation top

Answer: At the shell-to-bottom plate junction (B). It acts as a critical structural tie-in to distribute high shell bending stresses.

 

 

 

 

Q16. Bottom plate failure is mainly due to:

A) Pressure
B) Soil corrosion
C) Wind
D) Heat

Answer: Undetected soil-side corrosion (B)

 

 

 

 

Q17. Shell stress is proportional to:

A) Height of liquid
B) Paint
C) Color
D) Weld length

Answer: The height of the liquid column above that point (A).

 

 

 

 

Q18. Which reduces stress?

A) Increase height
B) Reduce fill level
C) Increase pressure
D) Remove thickness

Answer: Lowering the maximum fill level (B). This reduces the total hydrostatic head.

 

 

 

 

Q19. Thickness evaluation determines:

A) Color
B) Fitness for service
C) Inspection method
D) Welding type

Answer: To establish structural integrity and ongoing fitness for service (B).

 

 

 

 

Q20. Bottom inspection requires:

A) External only
B) Internal inspection
C) No inspection
D) Painting

Answer: An internal inspection (B). Out-of-service NDE (like MFL or UT scan) is required to evaluate floor plate condition accurately.

 

 

 

 

 

🔍 SECTION 3 — INSPECTION & INTERVALS (Q21–Q30)

Q21. Inspection interval is based on:

A) Age
B) Remaining life
C) Pressure only
D) Color

✔ B) Remaining life
➡️ Core governing factor

 

 

 

 

Q22. External inspection detects:

A) Bottom corrosion
B) Shell condition
C) Internal pitting
D) Soil corrosion

✔ B) Shell condition
➡️ External checks visible surfaces

 

 

 

 

Q23. Internal inspection detects:

A) External cracks
B) Bottom corrosion
C) Paint defects
D) Wind damage

✔ B) Bottom corrosion
➡️ Requires internal inspection

 

 

 

 

Q24. On-stream inspection means:

A) Tank empty
B) Tank in service
C) Tank dismantled
D) Tank repaired

✔ B) Tank in service
➡️ On-stream = operating condition

 

 

 

 

Q25. Maximum interval is:

A) RL × 2
B) RL ÷ 2
C) RL
D) RL + 10

✔ B) RL ÷ 2
➡️ Maximum interval rule

 

 

 

 

Q26. RBI allows:

A) Ignoring inspection
B) Adjusting interval
C) Removing corrosion
D) Eliminating thickness

✔ B) Adjusting interval
➡️ Risk-based inspection flexibility

 

 

 

 

Q27. Inspection determines:

A) Pressure only
B) Condition of tank
C) Color
D) Weld type

✔ B) Condition of tank
➡️ Inspection = condition assessment

 

 

 

 

Q28. Frequency increases when:

A) Corrosion increases
B) Thickness increases
C) Paint improves
D) Height decreases

✔ A) Corrosion increases
➡️ Faster degradation → more frequent inspection

 

 

 

 

Q29. Inspection must be documented by:

A) Operator
B) Inspector
C) Welder
D) Painter

✔ B) Inspector
➡️ Authorized inspector responsibility

 

 

 

 

Q30. Inspection plan is based on:

A) Risk + condition
B) Color
C) Weld size
D) Roof type

✔ A) Risk + condition
➡️ Core inspection planning logic

 

 

 

 

 

🧱 SECTION 4 — DAMAGE MECHANISMS (Q31–Q40)

Q31. MIC stands for:

A) Mechanical impact
B) Microbiological corrosion
C) Magnetic inspection
D) Material inconsistency

✔ B) Microbiological induced corrosion (MIC)
➡️ Bacteria-driven corrosion

 

 

 

 

Q32. CUI occurs due to:

A) Heat
B) Insulation moisture
C) Pressure
D) Welding

✔ B) Insulation moisture
➡️ Traps water → corrosion

 

 

 

 

Q33. Pitting corrosion is:

A) Uniform
B) Localized
C) Weld only
D) External only

✔ B) Localized
➡️ Pitting is concentrated damage

 

 

 

 

Q34. Settlement causes:

A) Color change
B) Stress concentration
C) Pressure drop
D) Temperature rise

✔ B) Stress concentration
➡️ Uneven settlement creates stress

 

 

 

 

Q35. Edge settlement affects:

A) Roof
B) Shell-bottom area
C) Nozzle only
D) Paint

✔ B) Shell-bottom area
➡️ Critical stress region

 

 

 

 

Q36. Uniform settlement is:

A) Dangerous always
B) Usually acceptable
C) Always failure
D) Impossible

✔ B) Usually acceptable
➡️ If uniform, less damaging

 

 

 

Q37. Bottom corrosion risk increases with:

A) Dry soil
B) Wet soil
C) Paint
D) Thickness

✔ B) Wet soil
➡️ Promotes corrosion

 

 

 

Q38. Thermal effects cause:

A) Settlement
B) Expansion/contraction
C) Corrosion
D) Welding

✔ B) Expansion/contraction
➡️ Thermal cycling effect

 

 

 

Q39. Damage mechanism selection depends on:

A) Color
B) Environment + service
C) Thickness only
D) Pressure only

✔ B) Environment + service
➡️ Determines damage type

 

 

 

Q40. Most critical tank failure area:

A) Roof
B) Bottom
C) Paint
D) Ladder

✔ B) Bottom
➡️ Most failures originate here

 

 

 

⚙️ SECTION 5 — REPAIRS / ALTERATIONS (Q41–Q50)

Q41. Repair means:

A) Change design
B) Restore original condition
C) Increase height
D) Replace entire tank

✔ B) Restore original condition
➡️ Repair definition

 

 

 

Q42. Alteration means:

A) Restore condition
B) Change design
C) Paint tank
D) Inspect

✔ B) Change design
➡️ Alteration definition

 

 

 

Q43. Reconstruction means:

A) Minor repair
B) Rebuilding tank
C) Painting
D) Inspection

✔ B) Rebuilding tank
➡️ Reconstruction concept

 

 

 

Q44. Welding repair requires:

A) Approval
B) Paint
C) Inspection only
D) Nothing

✔ A) Approval
➡️ Required before welding repair

 

 

 

Q45. Bottom replacement is:

A) Repair
B) Alteration
C) Reconstruction
D) Inspection

✔ A) Repair
➡️ Bottom replacement restores function

 

 

 

Q46. Shell course replacement is:

A) Repair
B) Alteration
C) Reconstruction
D) Painting

✔ C) Reconstruction
➡️ Major structural rebuild

 

 

 

Q47. Documentation is required for:

A) Inspection only
B) Repairs and alterations
C) Painting
D) Color change

✔ B) Repairs and alterations
➡️ Must be documented

 

 

 

Q48. Hydrotest after repair is:

A) Always required
B) Sometimes required
C) Never required
D) Only for paint

✔ B) Sometimes required
➡️ Depends on repair type

 

 

 

Q49.Who approves repair?

A) Operator only
B) Authorized inspector
C) Welder
D) Painter

✔ B) Authorized inspector
➡️ Final approval authority

 

 

 

Q50. Fitness-for-service decision is based on:

A) Thickness + condition
B) Color
C) Height
D) Paint

✔ A) Thickness + condition
➡️ Determines safety decision

 

 

 

 

🧠 PATTERN SUMMARY

🧮 Calculation logic:

  • Corrosion rate → thickness loss over time
  • Remaining life → usable thickness / CR
  • Inspection interval → RL ÷ 2

 

📏 Tank logic:

  • Bottom = highest risk
  • Height ↑ → pressure ↑ → stress ↑
  • Thickness ↓ → risk ↑

 

 

 

🔍 Inspection logic:

  • External → shell
  • Internal → bottom
  • RBI → adjust interval

 

 

 

⚙️ Repair logic:

  • Repair = restore
  • Alteration = change
  • Reconstruction = rebuild

 

 

want to know more? study our free lessons and quiz at:

API 653 Storage Tank Inspector Online Training Course

 

 

 

 

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

How to Get API Certified

Why API Certification? An API certification is more than just a qualification—it is a globally recognised credential that demonstrates your

Do You Want To Boost Your knowledge?

See our Coursses