Installation, Operation and Maintenance Manual (IOM): IOM constitutes part of the shipping document used for installation and operation as the name suggests. IOM also lists the volume and number of consumables such as bolts, gaskets, oil that is …
Fixed equipment is normally packed for outdoor storage of one year or as agreed with the purchaser. Rotating equipment should have package suitable for outdoor storage without maintenance for a period of six months or as agreed with purchaser. …
The manufacturer/fabricator is responsible for the quality of all their Manufactured and & Fabricated products, which includes not only goods workmanship, but also compliance with all codes, standards and specifications contained in the contractual agreements. This is regardless of whether …
Normally 4 weeks after placement of order or 2 weeks after submitting the critical documents, a kick off meeting is held. It is advisable to hold the KOM after one cycle of critical document turnaround in order to have …
Short listed bidders are invited for a face to face meeting with the client called clarification meeting or pre-purchase meeting at client’s premises. The intention of such meeting is: To explain what is wanted from the supplier and how …
As potential supplier’s proposal are received, they are reviewed by procurement (to see if supplier could adhere to the stipulated delivery and compare price with other suppliers); by quality engineer (to see if supplier is prepared to abide by the …
Click below Study our free lessons and quiz:
Depending on the criticality and complexity of the materials & equipment being procured, CLIENT and their assigned representatives may conduct out a pre-award audit or assessment of CONTRACTOR & VENDOR and any intended lower-tier- Supply Chain prior to the award …
Normally, 2-4 weeks after the kick off meeting or 2 weeks after submission of critical quality documents, the pre production meeting is held. It is advisable to hold the PIM after one cycle of critical document turnaround in order to …
Kick Off meeting: Normally 4 weeks after placement of order or 2 weeks after submitting the critical documents, a kick off meeting is held. It is advisable to hold the KOM after one cycle of critical document turnaround in order …