Continuous Improvement: At the completion of the inspection activities; a PDCA cycle (plan, do, check, act) review is taken as part of a continuous improvement program to determine which activities went well and where improvements should be made. Any …
It is the maximum gauge pressure at the top of a pressure vessel allowed by design or code calculations for a set temperature. When the working temperature decreases or significantly increases, material strength is reduced and therefore the pressure …
CONTRACTOR shall prepare the MRB that contains all the relevant certificates, test reports, drawings, calculations relating to the CONTRACT as per vendor document requirement list (VDRL). The format and content of Manufacturing Record Book shall be in …
The bidders are short listed based on fulfilling the quality and certification requirements, acceptable engineering proposal, cost and delivery. It is always recommended to have an internal meeting between client’s package team members when short listing suppliers. …
Prior to commencement of the quality surveillance as per Inspection and test plan (ITP) intervention points, the inspector should confirm that the SUPPLIER has the most current documents, drawings, etc. specified in the engineering design. Please …
Since we are talking about the management aspect of quality assurance, quality control and inspection, the basic rules remain the same regardless of the type of the package, for example, bulk material, fixed equipment or rotating equipment. Initially, …
Project Quality Plan (PQP) is normally required for criticality “1” packages. It is based on ISO 10000 5 Quality management — Guidelines for quality plans. It would have the same requirements as ISO 9001 QMS but intended for implementation at …
QSR can be based on Procurement status report (PSR) with focus on inspection. QSR is updated and turned around internally on weekly basis. Information in a typical QSR can include all of the information in a typical …
It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis. The Procurement Status Report normally shows: Name of package Name of supplier Name …
Before we start preparing the paperwork for packages, let us examine the essential ingredient for bid document. A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications. The …