Cost Time Report (CTR)
Prepare a Cost Time Report (CTR) for each package to calculate the budget in terms of inspection man days required […]
Bid Review
As potential supplier’s proposal are received, they are reviewed by: procurement (to see whether the supplier is […]
Bid Clarification or Pre-purchase meeting
Short listed bidders are invited for a face to face meeting with the client called bid clarification meeting or […]
Audit & Assessment
Audit & Assessment Depending on the criticality and complexity of the materials & equipment procured, the CLIENT may conduct […]
QA QC & Inspection Management Of Packages
[vc_separator style=”shadow” border_width=”7″] Click below Study our free lessons and quiz: [vc_separator style=”shadow” border_width=”7″]
Criticality Rating Of Packages
[vc_separator style=”shadow” border_width=”7″] Click below Study our free lessons and quiz: [vc_separator style=”shadow” border_width=”7″]
Audit & Assessment
Depending on the criticality and complexity of the materials & equipment being procured, CLIENT and their assigned representatives may conduct […]
Quality Plan
Project Quality Plan (PQP) is normally required for criticality “1” packages. It is based on ISO 10005 Quality management — […]
Inspection Status Report
ISR can be based on Procurement status report (PSR) with focus on inspection. ISR is updated and turned around […]
Procurement Status Report (PSR)
It is a good practice to have a PSR that acts as a dashboard for procurement and fabrication activities updated […]