As potential supplier’s proposal are received, they are reviewed by:

 

procurement (to see whether the supplier is capable of producing the equipment and material within the expected delivery schedule and also compare quoted price against other suppliers).

 

by quality engineer (to see if supplier is prepared to abide by the quality requirements, and whether the potential supplier has requested for any quality or certification exception or deviation that is acceptable; also look at sample project Quality Plan (QP) and Inspection and Test Plan (I T P) submitted by the potential supplier to verify if they are acceptable in principle.

The quality engineer plays an active role by performing a desk top review of supplier bid documents such as ISO & HSE certifications; do an NCR trend analysis on contractor previous packages; check ratio of quality personnel versus total personnel, etc.

The supplier proposal is also checked by the nominated package engineer by looking at the filled-in data sheet, sample drawings and whether any engineering Deviation or Concession requested that is acceptable.

The potential supplier may also have Queries or questions that should be responded by the client’s package engineer.

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

API Exam comes with Instant Final Scoring now

API Exam comes with Instant Final Scoring now As of April 2024; all candidates appearing for API exam shall receive instant confirmed scoring and maximum within 24 hours after exam from prometric. That is not all.   Candidates shall also

Current vs. Voltage in Welding

Welding current is like volume of water while voltage is like the water pressure just like When you are watering a plant with a hose. That is why; when you increase the voltage, it means you are having a higher

Do You Want To Boost Your knowledge?

See our Coursses