Before we start preparing the paperwork for packages, let us examine the essential ingredient for bid document.
A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications.
The ingredients for specifications are based on:
The outcome of the Front End Engineering Design (FEED). This is the initial assessment of the project identifying alternatives.
The Basis of Design (BOD) based on FEED result; also called basic design which tells you about the applicable codes and standards, the overall design philosophy, design life, etc.
The applicable construction codes and standards that you should comply with as the law of the land or being mandatory.
The location where the equipment is used; considering corrosion allowance over design life, and the most suitable material to resist environmental corrosion.
The type of process fluid and the performance requirement in order to select the right type of construction material against process corrosion.