Procurement Status Report (PSR)

Share This Post

 

It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis.

 

The Procurement Status Report normally shows:

  • Name of package
  • Name of supplier
  • Name of relevant team members (package engineer, quality engineer, buyer, expeditor, lead inspector)
  • Date the Purchase order signed off,
  • Dates for Kick Off Meeting (K O M), Pre Inspection Meeting (P I M), Fabrication Commencement Date, Bench Mark Dates Fabrication and Testing, latest expediting visit and report Number.
  • Dates for First release, last release, Required on Site (R O S) Date and the like.

 

Required on Site date is normally a couple of months after the release date in order to absorb any delay in manufacturing and release without affecting the project progress. 

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

Pro Tip for Non Conformity Report (NCR)

A Non-Conformance Report (NCR) is a formal quality control document that plays a vital role in recording, identifying, and addressing instances where products, materials, or processes do not meet applicable procedures, acceptance criteria, specifications, codes, standards, or contractual requirements. [/vc_column_text][/vc_column][/vc_row]

Do You Want To Boost Your knowledge?

See our Coursses