Preparing bid document

Share This Post

 

Before we start preparing the paperwork for packages, let us examine the essential ingredient for bid document.

 

A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications.

 

The ingredients for specifications are based on:

  • The outcome of the Front End Engineering Design (FEED). This is the initial assessment of the project identifying alternatives.
  • The Basis of Design (BOD) based on FEED result; also called basic design which tells you about the applicable codes and standards, the overall design philosophy, design life, etc.
  • The applicable construction codes and standards that you should comply with as the law of the land or being mandatory.
  • The location where the equipment is used; considering corrosion allowance over design life, and the most suitable material to resist environmental corrosion.
  • The type of process fluid and the performance requirement in order to select the right type of construction material against process corrosion.

 

Specifications should comply with applicable construction codes and standards as a minimum and also specify the acceptance criteria.

For example, welding specification for pressure vessel should be compliant with ASME Section 5 for how to perform the NDE examination but the acceptance criteria should be according to ASME 8 (Pressure Vessel Construction Code).

 

Specifications shall be included in the bid documents so the potential supplier or manufacturer knows what he should be complying with.

 

The procedures (WPS, NDE, Test and  QC Procedures) is then prepared by the supplier and approved by the client  after placement of purchase order.

These procedures shall be complying with the applicable specification enclosed within bid documents that eventually called purchase order once the contract is signed between the purchaser and supplier.

For Example, the fabricator would prepare a WPS (welding Procedure Specification) that should comply with Client’s specification for welding; reviewed and approved by the purchaser/client.

 

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

API Exam comes with Instant Final Scoring now

API Exam comes with Instant Final Scoring now As of April 2024; all candidates appearing for API exam shall receive instant confirmed scoring and maximum within 24 hours after exam from prometric. That is not all.   Candidates shall also

Current vs. Voltage in Welding

Welding current is like volume of water while voltage is like the water pressure just like When you are watering a plant with a hose. That is why; when you increase the voltage, it means you are having a higher

Do You Want To Boost Your knowledge?

See our Coursses