QSR can be based on Procurement status report (PSR) with focus on inspection.

 

QSR is updated and turned around internally on weekly basis.

 

Information in a typical QSR can include all of the information in a typical PSR; plus:

  • Latest inspection visit
  • Latest Inspection Report No.
  • Next Inspection Visit
  • Any major site observation report (SOR) & NCR
  • Tentative Dates for performance test or final test

 

Performance test for rotating equipment is aimed at measuring such parameters as speed, power, volume, and vibration.

 

The performance test for fixed equipment such as a pressure vessel or heat exchanger would normally be a pressure and leak test.

 

The performance test for a valve, would be pressure test, back pressure test and leak test.

 

Actuated valves would have additional tests such as torque and time required to open and close the valve under pressure.

 

 The performance test for bulk material can be a visual and traceability check and Mill Test Report (MTR) review. 

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

API 510 Online Training Course – Basic Facts

Basic Facts In this lesson, you shall learn about: ⇒ How To Apply For API 510 Exam, ⇒ What You Shall Expect on Exam Day, ⇒ Exam Time Management & ⇒ Exam Tips. What you should expect during API exam

Do You Want To Boost Your knowledge?

See our Coursses