Packing & Storage
Fixed equipment is normally packed for outdoor storage of one year or as agreed with the purchaser. Rotating equipment […]
Inspector Duties
The manufacturer/fabricator is responsible for the quality of all their Manufactured and & Fabricated products, which includes not only goods […]
Kick Off Meeting

Normally 4 weeks after placement of order or 2 weeks after submitting the critical documents, a kick off meeting is […]
Bid Clarification /Pre-purchase meeting

Short listed bidders are invited for a face to face meeting with the client called clarification meeting or pre-purchase […]
How Bids and Tenders are assessed?

As potential supplier’s proposal are received, they are reviewed by procurement (to see if supplier could adhere to the stipulated […]
Audit & Assessment

Depending on the criticality and complexity of the materials & equipment being procured, CLIENT and their assigned representatives may conduct […]
Pre-production or Pre-Inspection Meeting (PPM or PIM)

Normally, 2-4 weeks after the kick off meeting or 2 weeks after submission of critical quality documents, the pre production […]
Kick Off meeting

Kick Off meeting: Normally 4 weeks after placement of order or 2 weeks after submitting the critical documents, a kick […]
Inspector Duties

Inspector Duties: The manufacturer/fabricator is responsible for the quality of all their Manufactured and & Fabricated products, which includes not […]
Inspection Report

Inspection reports shall be written on a template in order to standardize the reporting system. Such form normally has sections […]