Bid Clarification or Pre-purchase meeting

Share This Post

 

Short listed bidders are invited for a face to face meeting with the client called bid clarification meeting or pre-purchase meeting at client’s premises. The intention of such meeting is:

  • To explain what is wanted from the supplier and how they fit within the project scenario.

 

  • To reiterate the package requirement to ensure that the prospective supplier fully understood the requirements in terms of engineering, fabrication, quality control and testing, certification and delivery.

 

  • To answer any Query the supplier may have and to finalize any issue that was still open in the comments sheet.

 

  • To meet supplier’s key personnel (project manager, document controller, quality engineer, discipline engineer).

 

The clarification meeting or pre-purchase meeting is normally chaired by the buyer from procurement department who also arranges and facilitates the meeting.

Client’s package team member such as quality and package engineers and any major engineering discipline shall attend such meeting explaining the salient features of the package from their perspective or answer any question, their supplier counterpart may have.

 

 

All important aspects of the package are discussed during the pre-purchase meeting, for example:

  • Buyer would finalized the delivery date (s); explain methods of communication, introduce project team members, any weekly meeting required (day, time), explain expediting methods (desk top expediting, field expediting) and finalize bench mark dates for submission of critical documents (data sheet, vendor document requirement list, quality plan and/or ITP) if the bid is successful. Supplier’s proposed fabrication plan is a good source to start with.
  • Client’s document controller would explain methods of document submission, review and return, turnaround time, periodical document status reporting, document numbering procedure, and document approval procedure.
  • Quality engineer explain quality assurance, inspection and testing requirements including certifications. It is a good practice to ask the supplier’s quality engineer to provide sample QP; ITP and go through it together, so the supplier’s quality engineer is better informed about how to prepare them. This exercise would drastically reduce the number of comments once these critical documents submitted.
  • Package engineer discusses engineering issues and identifies any outstanding engineering issues that need to be cleared before placement of order. Data sheet being the prime document while welding, material, electrical disciplines may also be discussed as the case may be.

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

Pro tip for API 1169 Pipeline Construction Inspector Exam

What are you expected to know for the exam?  API 1169 Pipeline Construction Inspectors is representing the client on new onshore pipeline construction. This means offshore pipeline and operation/maintenance of onshore pipeline is not in the scope. The API 1169

Pro tip for API 580 Risk based Inspection (RBI) Exam

What are you expected to know for the exam? The only reference document for API 580 Risk based Inspection (RBI) Exam is API RP 580, currently at 4th Edition (2023). The title of API 580 is “Elements of a Risk-Based

Do You Want To Boost Your knowledge?

See our Coursses