Prepare a Cost Time Report (CTR) for each package to calculate the budget in terms of inspection man days required during manufacturing.
You can use equipment criticality to assign a factor for calculating man days.
For example, forĀ an equipment with criticality ā1ā , assign a factor of ā1.6ā;
Now; if the equipment takes 6 months to be manufactured; considering 5 working days per week, you would need 6 X 22 (22 being working days in a month) multiplied by 1.6 (package criticality factor) = 211 man days of inspection.
For criticality ā2ā you can use a factor of ā1ā and so on.
Criticality ā3ā normally needs a final inspection only; while criticality ā4ā items are normally inspected at the point of receipt or at site.
You may want to add 25% to the total budget to account for uncertainties and any surprises such as:
- Ā repeat inspection due to NCR,
- Ā cancelled inspection by supplier,
- Ā delays,
- Ā enhanced inspection due to supplierās poor performance.