Before we start preparing the paperwork for packages, let us examine the essential ingredient for bid document. A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications. The …
Consists of general terms and conditions, data sheet and applicable relevant project specification. Data sheet is one of the critical documents that specifies the package main characteristics such input and output, type of fluid, inspection requirements, etc. …
PIM also called Pre-production Meeting (PPM) is normally held , 2-4 weeks after the kick off meeting or 2 weeks after submission of critical quality documents. Â It is advisable to hold the PIM after one cycle of …
https://static.inspector-training.com/uploads/2023/03/Packing-storage.mp4 Fixed equipment is normally packed for outdoor storage for one year or as agreed with the purchaser. Rotating equipment should have package suitable for outdoor storage without maintenance for a period of minimum six months or as agreed …
Normally, client forms a team for each package. The focal point for each package is the package engineer who may seek assistance from other engineering disciplines such as electrical, process, mechanical, material, welding, NDE and coating as and …
The supplier shall adhere to the instructions and reference documents included in the purchase order. In case of discrepancy between reference documents, normally, the following order of precedence is observed: Contract, Specific Conditions Contract, General Conditions Basis of …
EN 10 2 0 4 Metallic products, Types of inspection documents identifies 4 types of material certificates: 1 type: is a mere certificate of compliance issued by manufacturer. 2 type: includes the chemical composition and mechanical test report but …
Management of Change (MOC) is a systematic approach dealing with the proposed changes and it’s effect on other activities, processes and equipment. Changes need to be approved by the client before being implemented by the SUPPLIER. …
Normally 4 weeks after placement of purchase order or 2 weeks after submitting the critical documents, a kick off meeting is held. It is advisable to hold the Kick off meeting after one cycle of critical document review …
I O M constitutes part of the shipping document used for installation and operation as the name suggests. Â I O M also lists the volume and number of consumables such as bolts, gaskets, oil that is needed for …