Project Quality Plan (PQP) is normally required for criticality “1” packages. It is based on ISO 10005 Quality management — Guidelines for quality plans. It would have the same requirements as ISO 9001 QMS but intended for implementation at project …
ISR can be based on Procurement status report (PSR) with focus on inspection. ISR is updated and turned around internally on weekly basis. Information in a typical ISR can include all of the information in a typical PSR; plus: …
It is a good practice to have a PSR that acts as a dashboard for procurement and fabrication activities updated on weekly basis. The Procurement Status Report normally shows: Name of package Name of supplier Name of relevant team …
Each package is assigned a criticality rating; ranging from 1 through 4, with criticality ‘’1’’ being the highest. There are several factors for assigning the criticality rating but the most important ones for assigning high criticality rating, would be: …
Since we are talking about the management aspect of quality assurance, quality control and inspection, the basic rules remain the same regardless of the type of the package, e.g., bulk material, fixed equipment or rotating equipment. Initially, the focus …
Before we start preparing the pre-bid paperwork for packages, let us examine the essential ingredient for pre-bid document. A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications. The …
Before the equipment become fully operational, it needs to be pre commissioned to see whether it is in working order and then commissioned together with a series of other equipment to see whether the whole group of equipment works in …
Installation, Operation and Maintenance Manual (IOM): IOM constitutes part of the shipping document used for installation and operation as the name suggests. IOM also lists the volume and number of consumables such as bolts, gaskets, oil that is …
Fixed equipment is normally packed for outdoor storage of one year or as agreed with the purchaser. Rotating equipment should have package suitable for outdoor storage without maintenance for a period of six months or as agreed with purchaser. …
The manufacturer/fabricator is responsible for the quality of all their Manufactured and & Fabricated products, which includes not only goods workmanship, but also compliance with all codes, standards and specifications contained in the contractual agreements. This is regardless of whether …