Order of Precedence for Reference Documents

Share This Post

 

The supplier shall adhere to the instructions and reference documents included in the purchase order.

 

In case of discrepancy between reference documents, normally, the following order of precedence is observed:

  1. Contract, Specific Conditions
  2. Contract, General Conditions
  3. Basis of Design (B O D)
  4. Documents that require deviation to be approved by Client including Design Criteria, Philosophies, PFDs, Plot Plans
  5. Documents that require deviation to be approved by Principal Contractor including Specifications,  drawings.

Click below Study our free lessons and quiz:

Subscribe To Our Newsletter

Get updates and learn from the best

More To Explore

571

Galavanic Corrosion

When two dissimilar materials are in contact with each other, there is a high possibility of one of them act as sacrificial anode and corrode. The one that corrodes looses electrode and turns positive or becomes anodic while the other

API 653 exam questions
Api 653

API 653 exam tips formulas

  🛠️ Formula & Concept Adjustments   1. The t min formula (API 653 Section 4.3.3.1)   ⚠️ Critical Catch: For an existing tank evaluation under API 653, the formula actually uses (H-1) instead of just H for the first

Do You Want To Boost Your knowledge?

See our Coursses