The bidders are short listed based on fulfilling the quality and certification requirements, acceptable engineering proposal, cost and delivery. It is always recommended to have an internal meeting between client’s package team members when short listing suppliers. …
Prior to commencement of the quality surveillance as per Inspection and test plan (ITP) intervention points, the inspector should confirm that the SUPPLIER has the most current documents, drawings, etc. specified in the engineering design. Please …
Since we are talking about the management aspect of quality assurance, quality control and inspection, the basic rules remain the same regardless of the type of the package, for example, bulk material, fixed equipment or rotating equipment. Initially, …
Project Quality Plan (PQP) is normally required for criticality “1” packages. It is based on ISO 10000 5 Quality management — Guidelines for quality plans. It would have the same requirements as ISO 9001 QMS but intended for implementation at …
QSR can be based on Procurement status report (PSR) with focus on inspection. QSR is updated and turned around internally on weekly basis. Information in a typical QSR can include all of the information in a typical …
It is a good practice to have a PSR used as a dashboard for procurement and fabrication activities. PSR should be updated on weekly basis. The Procurement Status Report normally shows: Name of package Name of supplier Name …
Before we start preparing the paperwork for packages, let us examine the essential ingredient for bid document. A Package whether standalone or part of a bigger EPCM project (Engineering Procurement Construction Management) is based on specifications. The …
Consists of general terms and conditions, data sheet and applicable relevant project specification. Data sheet is one of the critical documents that specifies the package main characteristics such input and output, type of fluid, inspection requirements, etc. …
PIM also called Pre-production Meeting (PPM) is normally held , 2-4 weeks after the kick off meeting or 2 weeks after submission of critical quality documents. It is advisable to hold the PIM after one cycle of …
https://static.inspector-training.com/uploads/2023/03/Packing-storage.mp4 Fixed equipment is normally packed for outdoor storage for one year or as agreed with the purchaser. Rotating equipment should have package suitable for outdoor storage without maintenance for a period of minimum six months or as agreed …