Inspection Report shall be written on a template in order to standardize the reporting system. Inspection report normally has sections for: vendor details, reference document (QC procedures, drawings and specially); description of what activity witnessed or inspected and …
Means confirming that the construction materials proposed are the actual materials used during construction is a typical inspection activity. The inspector should: Confirm the correct material type and grade. Confirm the origin of the material. Check material size and …
Prepare a master Inspection register where each package is assigned an excel page named after the package and has bench mark phases (purchase order date, test dates, Kick Off Meeting date, Pre Inspection Meeting (PIM) date, release date); …
For each assignment, prepare an inspection pack that as a minimum would consist of: Notification of Inspection (NOI), Purchase Order, Inspection and Test Plan, approved and relevant QC Procedures, inspection reporting template, NCR and punch list forms, and any …
ITP is also called Quality Control Plan (QCP) but should not be mistaken with Project Quality Plan (PQP). PQP is purely a quality assurance exercise and tell you how the quality measures are planned for each topic such …
For less complex packages such as bulk materials and off the shelf components, we need very few documents such as certificate of compliance (Cf C) or material test report (MTR). However, for criticality “1” and “2” equipment that …
Deviation Request: During bidding stage, the potential supplier should notify the client of any deviations requested by providing the reason for deviation. These deviations if accepted; shall constitute part of the purchase order. Concession request: Concession means …
Each package is assigned a criticality rating; ranging from 1 through 4, with criticality ‘’1’’ being the highest. There are several factors for assigning the criticality rating but the most important ones are: Whether the package is long …
Prepare a Cost Time Report (CTR) for each package to calculate the budget in terms of inspection man days required during manufacturing. You can use equipment criticality to assign a factor for calculating man days. For example, for …
As potential supplier’s proposal are received, they are reviewed by: procurement (to see whether the supplier is capable of producing the equipment and material within the expected delivery schedule and also compare quoted price against other suppliers). …