Normally, client forms a team for each package. The focal point for each package is the package engineer who may seek assistance from other engineering disciplines such as electrical, process, mechanical, material, welding, NDE and coating as and …
The supplier shall adhere to the instructions and reference documents included in the purchase order. In case of discrepancy between reference documents, normally, the following order of precedence is observed: Contract, Specific Conditions Contract, General Conditions Basis of …
EN 10 2 0 4 Metallic products, Types of inspection documents identifies 4 types of material certificates: 1 type: is a mere certificate of compliance issued by manufacturer. 2 type: includes the chemical composition and mechanical test report but …
Management of Change (MOC) is a systematic approach dealing with the proposed changes and it’s effect on other activities, processes and equipment. Changes need to be approved by the client before being implemented by the SUPPLIER. …
Normally 4 weeks after placement of purchase order or 2 weeks after submitting the critical documents, a kick off meeting is held. It is advisable to hold the Kick off meeting after one cycle of critical document review …
I O M constitutes part of the shipping document used for installation and operation as the name suggests. Â I O M also lists the volume and number of consumables such as bolts, gaskets, oil that is needed for …
The manufacturer is responsible for the quality of  their products, which includes not only good workmanship, but also compliance with codes, standards and specifications noted within purchase order. This is regardless of whether the manufacturer has made …
Inspection Report shall be written on a template in order to standardize the reporting system. Inspection report normally has sections for: vendor details, Â reference document (QC procedures, drawings and specially); description of what activity witnessed or inspected and …
Means confirming that the construction materials proposed are the actual materials used during construction is a typical inspection activity. The inspector should: Confirm the correct material type and grade. Confirm the origin of the material. Check material size and …
Prepare a master Inspection register where each package is assigned an excel page named after the package and has bench mark phases (purchase order date, test dates, Kick Off Meeting date, Pre Inspection Meeting (PIM) date, release date); …